Conductor pipe analysis
OFFSHORE This typical project consists in a design verification of a conductor pipe. Its strength has to be checked against the extreme conditions as well
OFFSHORE This typical project consists in a design verification of a conductor pipe. Its strength has to be checked against the extreme conditions as well
OFFSHORE The project consists in assessing the hydrostatic stability of a drilling barge. This barge is made of modular floating elements (Combifloat), on which the
This tender is able to erect the DES with its own main crane on platform beams up to 35m above MSL. Three main lifts only are required to complete the installation.
The derrick is supported by the skid beams of the platform deck which is perpendicular to the tender axes. These skids beams can be maximum 52,5ft apart.
Due to lack of sea access, use of a conventional offshore unit was not possible. This led to this unique design of a modular barge able to drill eleven exploration wells between 10m and 50m water depth in Uganda Lake Albert.
RIG DESIGN Key Points: – The interface between jacket Well bay and jack-up – Integration of HPHT well constraints – Integration of well services equipment