Basic and detailed engineering of a self-elevating structure for a 35° slant rig. This rig was initially designed to drill water wells with no BOPs. The deeper drilling depth requires a BOP system, which was not originally planned. The structure was designed to lift the drilling truck by 3,7m to allow installation of 11” or 7” BOP stacks.

key facts
- Rig location: Gabon
- Clients / Partners: Perenco
- Project Phase: Engineering
- Contract Start/Finish: September 2009-2010